Subcontract review checklist: 10 things to check before you sign

Most subcontract problems are not hidden. They sit in plain sight on page two, and nobody checks them until the first invoice is late. Here are the ten points we check on every contract.

1. Do the line totals equal quantity × rate?

It sounds basic, yet it is the most common error we find. In one sample contract, the line amounts added up to 141,650 while the contract total said 112,650. When the numbers disagree, every future invoice becomes an argument. Recalculate every line yourself.

2. Is there a deadline for approving invoices?

"Payment within 45 days of approval" means nothing if approval itself has no deadline. Ask for wording such as "invoices are approved or rejected with reasons within 7 days of submission".

3. Is the project duration actually written down?

"As per the approved programme" is not a date. If delay penalties apply, they should apply only to a programme both parties signed.

4. Can only one side terminate?

Many contracts let the main contractor terminate for "slow progress" while giving the subcontractor no right at all. Ask for an objective test and a matching right for you if payments are 30 days late.

5. Are delay penalties capped?

A cap of around 10% of the contract value is common. No cap means unlimited risk.

6. What happens when quantities change?

Fixed rates are fine within a range. Beyond roughly ±20%, rates should be agreed again.

7. Can items be added or cancelled at the same rates?

Variations above a set percentage of the contract value should be priced separately and in writing.

8. How much is retained, and when is it released?

Retention of 5–10% is normal. Make sure the release date is tied to a clear event, such as final acceptance.

9. Is the confidentiality penalty reasonable?

"A penalty in proportion to the damage" with no cap is an open cheque. Ask for a fixed maximum.

10. Who carries the main contract's obligations?

Some subcontracts pass every obligation of the main contract down to you. Make sure you have actually seen the documents you are agreeing to.

Want a second pair of eyes?

We review subcontracts in Arabic and English within 24 hours and send a report with the risks, the wrong numbers and a ready-to-send email asking for changes. See a sample report or send your contract.

This article is general information, not legal advice.